The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to ... ) 25 person months (B) 75 person months (C) 62.5 person months (D) 72.5 person months Answer : (C) 62.5 person months ...
A software project was estimated at 352 Function Points (FP). A four person team will be assigned to this project consisting of an architect, two programmers, and a tester. The salary of the architect is Rs.80,000 per month, the ... ) Rs.28,16,000 (2) Rs.20,90,000 (3) Rs.26,95,000 (4) Rs.27,50,000 Answer : (4) Rs.27,50,000Â ...
A software company needs to develop a project that is estimated as 1000 function points and is planning to use JAVA as the programming language whose approximate lines of code per function point is accepted as 50. Considering a=1. ... ? (1) 11.2 months (2) 12.2 months (3) 13.2 months (4) 10.2 months Answer : (2) 12.2 months...
Which one of the following statements, related to the requirements phase in Software Engineering, is incorrect ? (A) Requirement validation is one of the activities in the requirements phase. (B) ... . (D) Function points is one of the most commonly used size metric for requirements. Answer : (C) “Modelling-oriented approach” is one of the methods for specifying the functional specifications. ...
Consider f(N) = g(N) + h(N) Where function g is a measure of the cost of getting from the start node to the current node N and h is an estimate of additional cost of getting from the current ... ? (A) A* algorithm (B) AO* algorithm (C) Greedy best first search algorithm (D) Iterative A* algorithm Answer : (C) Greedy best first search algorithm...