by
anonymous
asked
Jan 12, 2021
21 views
P and Q can do a piece of job in 24 days; Q and R can do it in 30 days while R and P can finish it in 40 days. If P, Q, Rworks together, in how many days will they finish the job? In how many days will each one of them finish it, working alone? A) 15,25,35,45 B) 20,30,40,120 C) 20,30,40,50 D) 20,25,30,60
P and Q can do a piece of job in 24 days; Q and R can do it in 30 days while R and P can finish it in 40 days. If P, Q, Rworks together, in how many days will they finish the job? In how many days will each ... finish it, working alone? A) 15,25,35,45 B) 20,30,40,120 C) 20,30,40,50 D) 20,25,30,60
Answer : B Time taken by (P + Q) to finish the job = 24days. (P + Q)'s 1 day's job = 1/24 Time taken by (Q +R) to finish the job = 30days. (Q + R)'s 1 day's job = 1/30 Time taken by (R + P) to finish the ... - {(P + Q)'s 1 day's job } = (1/20 -1/24)=1/120 Hence, R alone can finish the job in 120 days....
View solution