............................ is the sequence of activities which determines the total project duration.
a. Critical path
b. Network
c. Non-critical activities
d. None of these
0 like 0 dislike

1 Answer

a. Critical path
0 like 0 dislike

Related questions

Activities lying on critical path are called ............................ a. Critical activities b. Non-critical activities c. Dummy activities d. None of these
Answer : a. Critical activities...

View solution
0 like 0 dislike
1 answer

.......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these
Answer : b. Total float...

View solution
0 like 0 dislike
1 answer

......................... is a series of activities related to a project. a. Network b. Transportation Model c. Assignment model d. None of these
Answer : a. Network...

View solution
0 like 0 dislike
1 answer

....................... deals with the concepts such as critical path, float, events, etc. a. Game theory b. Decision theory c. Queuing theory d. Network analysis
Answer : d. Network analysis...

View solution
0 like 0 dislike
1 answer

Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float
Answer : A. Total Float....

View solution
0 like 0 dislike
1 answer