Activities lying on critical path are called ............................ a. Critical activities b. Non-critical activities c. Dummy activities d. None of these Answer : a. Critical activities...
.......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these Answer : b. Total float...
......................... is a series of activities related to a project. a. Network b. Transportation Model c. Assignment model d. None of these Answer : a. Network...
....................... deals with the concepts such as critical path, float, events, etc. a. Game theory b. Decision theory c. Queuing theory d. Network analysis Answer : d. Network analysis...
Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float Answer : A. Total Float....