............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these Answer : a. Critical path...
An activity which must be completed before commencement of one or more other activities is called................................. a. Successor activity b. Predecessor activity c. Dummy activity d. None of these Answer : b. Predecessor activity...
All activities lying on critical path have slack time equal to (A) 0 (B) 1 (C) 2 (D) None of above Answer : (A) 0...
Activities that cannot be started until one or more of the other activities are completed, are called.......................................... a. Dummy activities b. Initial activities c. Successor activities d. Predecessor activities Answer : c. Successor activities...
The variables whose coefficient vectors are unit vectors, are called ...................... a. Unit variables b. Basic variables c. Non-basic variables d. None of these Answer : b. Basic variables...
50.5k questions
47.1k answers
240 comments
7.0k users