Overhead system can be designed for operation up to 400 kV.

0 like 0 dislike

Related questions

What would happen if a power transformer designed for operation on 50 Hz (frequency) were connected to a 500 Hz (frequency) source of the same voltage:  (A) Eddy Current and Hysteresis losses will be ... Current will be too much high  (C) Transformer may start to smoke and burn  (D) No effect
Answer : What would happen if a power transformer designed for operation on 50 Hz (frequency) were connected to a 500 Hz (frequency) source of the same voltage:  (A) Eddy Current and Hysteresis losses will be ... will be too much high  (C) Transformer may start to smoke and burn  (D) No effect ...

View solution
0 like 0 dislike
1 answer


Answer : Air blast circuit breakers for 400 kV power system are designed to operate in 50 millisecond. ...

View solution
0 like 0 dislike
1 answer

Why ACSR conductor is used for overhead lines?
Answer : It has high tensile strength ...

View solution
0 like 0 dislike
1 answer

Draw and explain integrated duration curve used in system operation. 
Answer : Diagram of integrated duration curve used in system operation: Explanation:  Integrated duration curve is obtained from load duration curve. It is drawn in between load on Y-axis in KW/MW and the X- ... a particular time of a day can also be shown on a curve which is called as mass curve.  ...

View solution
0 like 0 dislike
1 answer

Overhead system can be designed for operation up to (a) 11 kV (b) 33 kV (c) 66 kV (d) 400 kV
Answer : (c) 66 kV...