The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to complete the project using the effort formula of basic COCOMO given below: E = a(KLOC)b Assume that the values of a and b are 2.5 and 1.0 respectively. (A) 25 person months (B) 75 person months (C) 62.5 person months (D) 72.5 person months
0 like 0 dislike

1 Answer

(C) 62.5 person months 
0 like 0 dislike

Related questions

0 like 0 dislike
1 answer

A software project was estimated at 352 Function Points (FP). A four person team will be assigned to this project consisting of an architect, two programmers, and a tester. The salary of the architect is Rs.80,000 per month, the ... ) Rs.28,16,000 (2) Rs.20,90,000 (3) Rs.26,95,000 (4) Rs.27,50,000
Answer : (4) Rs.27,50,000 ...

View solution
0 like 0 dislike
1 answer

Suppose the function y and a fuzzy integer number around -4 for x are given as y=(x-3)2+2 Around -4={(2,0.3), (3,0.6), (4,1), (5,0.6), (6,0.3)} respectively. Then f(Around - 4) is given by: (A) {(2,0.6), (3,0.3), ... 6), (3,1), (6,0.6), (11,0.3)} (D) {(2,0.6), (3,0.3), (6,0.6), (11,0.3)}
Answer : (C) {(2,0.6), (3,1), (6,0.6), (11,0.3)}...

View solution
0 like 0 dislike
1 answer

While estimating the cost of software, Lines of Code (LOC) and Function Points (FP) are used to measure which one of the following? (A) Length of code (B) Size of software (C) Functionality of software (D) None of the above
Answer : (B) Size of software...

View solution
0 like 0 dislike
1 answer
image

Given a Non-deterministic Finite Automation (NFA) with states p and r as initial and final states respectively transition table as given below  The minimum number of states required in Deterministic Finite Automation (DFA) equivalent to NFA is (A) 5 (B) 4 (C) 3 (D) 2
Answer : (C) 3 ...

View solution
0 like 0 dislike
1 answer

50.5k questions

47.1k answers

240 comments

7.0k users