On Rajdhani routes testing frequency of rail testing for rail section of 60kg with annual
GMT 80, will be.
(i) 4 months
(ii) 1 1ā„2 months
(iii) 1 months*
(iv) None of above.
0 like 0 dislike

1 Answer

(iii) 1 months*
0 like 0 dislike

Related questions

For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.
Answer : (ii) After passage of every 40 GMT traffic during test free period.*...

View solution
0 like 0 dislike
1 answer

If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6
Answer : ii) 5.7*...

View solution
0 like 0 dislike
1 answer

Addition gain of 10 db is used for testing. (i) ā€˜Dā€™ marked rails on single lines. (ii) ā€˜Dā€™ marked rails on double lines. (iii) Testing on single line and ā€˜Dā€™ marked rails on double/multiple lines section.* (iv) None of above.
Answer : (iii) Testing on single line and ā€˜Dā€™ marked rails on double/multiple lines section.*...

View solution
0 like 0 dislike
1 answer

What is the testing frequency of new AT weld ? (i) Just after the welding (ii) After 7 days of welding (iii) With in the one month of welding* (iv) None of the above
Answer : iii) With in the one month of welding*...

View solution
0 like 0 dislike
1 answer

After declare good in USFD testing what is the joggling criteria ? (i) Joggle will be open from the AT weld* (ii) Joggling with two far end bolting (iii) joggling with four tight bold (iv) None of the above
Answer : (i) Joggle will be open from the AT weld*...

View solution
0 like 0 dislike
1 answer

50.5k questions